Centrum Černý Most

Centrum Černý Most

Shopping Mall

Centrum Černý Most

Following its completion, the building will serve as a multi-purpose shopping and entertainment centre. It consists of a set of four sections separated by expansion joints with one underground and two aboveground floors of an L-shaped layout and maximum dimensions of 250 x 360 m. The underground floor will be used mainly for parking and the aboveground floors will feature malls surrounded by retail units. A major part of the roof will house mechanical and utility equipment and a car park. The foundation system of the building uses large-diameter bored piles with bored heads as well as strip foundations. The frame of the building is made of columns and underground perimeter walls, beams, girders, parapet beams and pre-stressed Spiroll panels combined with precast filigree elements and pre-stressed cast-in-place concrete beams.

Dimensions:    
Basic span:   8.1 x 8.1 m
Construction part:         A1        123.0 x 117.5 m
         A2 87.5 x 119.0 m
         B 105.0 x 105.0 m
         C 145.5 x 108.0 m

 

Project Highlights

The project features a post-tensioned precast concrete/cast-in-place concrete structure of the multiplex cinema ceiling slab. It consists of post-tensioned cast-in-place concrete beams in combination with semi-precast filigran slabs.

Key Data

Location:Prague - Černý Most
Type of Construction:Shopping Mall
Investor:Centrum Černý Most, a.s. (Unibail-Rodamco Česká republika, s.r.o.)
Designer:HELIKA a.s.
Start of Construction:11 / 2011
End of Construction:07 / 2012
Contract Value: